Project Information
Once completed Marylebone Square will provide apartments, retail space, parking and a range of community facilities, including a central courtyard space for Marylebone Farmers’ market.
To support the construction methodology employed by A J Morrisroe + Sons for the 3 level basement, we installed 456nr 750mmdiameter secant piles for the 230m perimeter secant piled wall. In addition to 36nrtemporary piles with plunged steel columns, which were designed to provide support to tower cranes, a UKPN room and a logistics gantry slab.
Piling works were sequenced with A J Morrisroe +Sons to ensure frictionless onsite delivery.